Measurement and Simulation of Hydro-Generator's Asynchronous Operation
2022
Journal of Energy - Energija
The extended testing of hydro-generator with Pelton turbine (rated 35 MVA) was performed on a generator whose lifespan expired and it was going to be replaced. This was the perfect opportunity to do some specific and uncommon testing. The complex testing plan was designed in order to enable recording of as much relevant data as possible (electrical, electromechanical, mechanical). Therefore, in some phases of testing, 29 to 44 quantities were measured simultaneously. Among the tests, there are
doi:10.37798/2010591-4274
fatcat:vyyki5qwbvf7xoo4ru34dbjqle