A copy of this work was available on the public web and has been preserved in the Wayback Machine. The capture dates from 2020; you can also visit the original URL.
The file type is application/pdf
.
Construction monitoring on the unloading process of steel roof for Guilin Liangjiang International Airport Terminal T2
2020
MATEC Web of Conferences
The main building of Guilin Liangjiang International Airport Terminal T2 adopts the steel reinforced concrete frame structure, the central roof uses the spatial solid web arch support and single-shell steel structural system with the largest supporting arch span of 120 meters, and the single-shell steel structural system is connected with the spatial solid web arch through diagonal bracing. The large-span space steel structure of the roof had a large building area, and more than 300 lattice
doi:10.1051/matecconf/202031909002
fatcat:yyvpfz3xljau7er7f2xsxh32ye