Rehabilitating a Life Line: Inspecting and Repairing the Hultman Aqueduct in Metropolitan Boston

Paul Savard, Peter McGovern
2011 Pipelines 2011   unpublished
The Massachusetts Water Resources Authority (MWRA) provides water to over 2.2 million people and 51 communities serving greater Boston and central Massachusetts. They are undertaking a $57 million construction project to rehabilitate the 13.4-mile long, 11.5-foot diameter Hultman Aqueduct, including: inspection and repair of the existing aqueduct pipe and construction of several large diameter valve chambers to house connections between the existing Aqueduct and the new MetroWest Tunnel. This
more » ... per will focus on the planning, inspection, and repair of the inside of the Hultman Aqueduct that has been completed to date for the first 10 miles. Because the Aqueduct could not be inspected and the exact extent of repairs quantified before the construction contract was awarded, a number of challenges needed to be considered.