Guidelines for inservice testing at nuclear power plants
[report]
1995
unpublished
The staff of the U.S. Nuclear Regulatory Commission (NRC) gives licensees guidelines and recommendations for developing and implementing programs for the inservice testing of pumps and valves at commercial nuclear power plants. The staff discusses the regulations; the components to be included in an inservice testing program; and the preparation and content of cold shutdown justifications, refueling outage justifications, and requests for relief from the American Society of Mechanical Engineers
doi:10.2172/50942
fatcat:6dgvkgurxfcvbjcau3dgv6jomu