Advanced Reactors Transition Program Resource Loaded Schedule
[report]
1999
unpublished
The Advanced Reactors Transition (ART) Resource Loaded Schedule (RLS) provides a cost and schedule baseline for managing the project elements within the ART Program. The Fast Flux Test Facility (FFTF) activities are delineated through the end of FY 2000, assuming continued standby. The Nuclear Energy (NE) Legacies and Plutonium Recycle Test Reactor (PRTR) activites are delineated through the end of t h e deactivation process. This document reflects the 1 Oct 1999 baseline. TRADEMARK OiSCLAiMER.