TAGUCHI METHOD FOR THREE-STAGE ASSEMBLY FLOW SHOP SCHEDULING PROBLEM WITH BLOCKING AND SEQUENCE-DEPENDENT SET UP TIMES
2013
Journal of Engineering Science and Technology
This article considers a three-stage assembly flowshop scheduling problem minimizing the weighted sum of mean completion time and makespan with sequence-dependent setup times at the first stage and blocking times between each stage. To tackle such an NP-hard, two meta-heuristic algorithms are presented. The novelty of our approach is to develop a variable neighborhood search algorithm (VNS) and a well-known simulated annealing (SA) for the problem. Furthermore, to enhance the performance of the