Comparative Study of Pipeline Deliverables using Deterministic and Stochastic Models
2019
European Journal of Engineering Research and Science
This study aim to proffer solution to the factors causing delay is pipeline construction project deliverables, it compared deterministic model (variable with certainty) and stochastic model (variable with uncertainty), with Six (6) planned project schedules of Brownfield Energy Service Limited for pipeline construction. Time assigned to critical activities, identified from a network analysis, with the aid of the Critical Path Method, expected mean time, both deterministic and stochastic