Simulation of load displacement in parallel lines using series connected tapped reactor
2008
2008 International Conference on High Voltage Engineering and Application
Different parallel transmission lines can be utilized when there is a power flow from a surplus generation area to a load centre in a meshed power grid. The current distribution in these lines depends on the inverse value of the line impedances. The current path with the lowest impedance will reach its maximum transmission capacity considerably earlier than the other parallel paths. It thus determines the maximum transmittable power, although the other parallel paths are not loaded to full