Last Planner System – the Need for New Metrics
2017
25th Annual Conference of the International Group for Lean Construction
unpublished
Several metrics have been used to evaluate the planning performance within the Last Planner System (LPS). Percent Planned Complete (PPC), which measures the reliability of weekly work planning, is the most commonly used metric. However, studies have shown the need to complement PPC with other metrics to measure performance. Researchers have developed many metrics to assess the makeready process, workflow reliability, and weekly work planning. Many of those metrics were either inconsistently