ANALYZING PROCUREMENT ROUTE SELECTION FOR ELECTRIC POWER PLANTS PROJECTS USING SMART
2015
Journal of Civil Engineering and Management
The decision of selecting the appropriate procurement/delivery system for large investment construction projects is a critical and challenging task for clients, and therefore a significant factor for the project's success. Complex projects as electric power plants can involve managing multiple contracts or subcontracts simultaneously or in sequence. The aim of this paper is to develop, and analyze a decision support tool to select the most efficient procurement/delivery system for multiple
doi:10.3846/13923730.2014.971131
fatcat:7z4myo3vxjb7redcns47zrie3y