Qualitative and quantitative project risk assessment using a hybrid PMBOK model developed under uncertainty conditions
2020
Heliyon
This study presented a qualitative and quantitative project risk assessment using a hybrid PMBOK model developed under uncertainty conditions. Accordingly, an exploratory and applied research design was employed in this study. The research sample included 15 experienced staff working in main and related positions in Neyr Perse Company. After reviewing the literature and the Project Management Body of Knowledge (PMBOK), 32 risk factors were identified and their number reduced to 17 risks using