Evaluation of In-situ Loading Test and at Deep Pleistocene Clay Layer for Settlement Prediction of Highway Bridge
2018
Japanese Geotechnical Journal
For the design of pipe foundation of large-span bridge, in-situ loading test on the deep Pleistocene clay layer was carried out. The loading plate, the diameter of which was 250mm, was placed on the Pleistocene clay layer at 70 m depth utilizing the bore hole. The settlement was observed for 9 months, in which the step loading was given by the hydraulic jack. Measured settlement showed the periodic fluctuations related with the tidal change, and the settlement continued with time and the