Analysis on Determining of the Purchase Price in the Repurchase Stage of a BT Project: A Case of Rail Transportation Project
2015
Proceedings of the 5th International Symposium on Knowledge Acquisition and Modeling
unpublished
The core issue about the risk management of the BT project was discussed in this paper, which presented the schemes of risk allocation between the government and the contractor. According to the analysis on the relationship of the risk factors bore by the government and the purchase price, the calculating method of purchase price were summarized and contrasted. Lastly, in the light of above analysis result, a case study was involved in this dissertation to verify the aforementioned research results.
doi:10.2991/kam-15.2015.74
fatcat:hxld2vtppbcjhdkaczo4j3isxi