Conversion Function and Relationship of Loss of Load Expectation Indices on Two Kinds of Load Duration Curve
두 종류의 부하곡선에 관한 공급지장시간기대치(LOLE)의 상호 변환관계성

Yeonchan Lee, Ungjin Oh, Jaeseok Choi, Junmin Cha, Hongseok Choi, Donghun Jeon
2017 The Transactions of The Korean Institute of Electrical Engineers  
This paper develops a conversion function and method transforming from daily peak load curve used LOLE D [days/ year] to hourly load curve used LOLE H [hours/year]and describes relationship between LOLE D [days/year] and LOLE H [hours/year]. The indices can not only be transformed just arithmetically but also have different characteristics physically because of using their different load curves. The conversion function is formulated as variables of capacity and forced outage rate of generator,
more » ... ourly load daily load factor and daily peak load yearly load factor, etc. Therefore, the conversion function (  ) can not be simple. In this study, therefore, the function is formulated as linear times of separated two functions. One is an exponential formed conversion function of daily load factor. Another is formulated with an exponential typed conversion function of daily peak load yearly load factor. Futhermore, this paper presents algorithm and flow chart for transforming from LOLE D [days/year] to LOLE H [hours/year]. The proposed conversion function is applied to sample system and actual KPS(Korea Power System) in 2015. The exponent coefficients of the conversion functions are assessed using proposed method. Finally, assessment errors using conversion function for case studies of sample system and actual system are evaluated to certify the firstly proposed method.
doi:10.5370/kiee.2017.66.3.475 fatcat:kh5heyttpvh5ve3h6rzoam4z5i