ANALISA GANGGUAN HUBUNG SINGKAT DENGAN MENGGUNAKAN ETAP 12.6.0 PADA PT X

Badaruddin Badaruddin
2017 Jurnal Teknik  
ConstructionofcoalhandlingfacilityPTXdemandingtheneedforan analysisofthe equipmentratingcircuitbreaker(CircuitBreaker),sothatthe CircuitBreaker(CB)can secure thepowersystemagainstharmfulinterference,especiallyinterference symmetrical short-circuitthree-phase.Foritwas doneastudyofshortcircuitintheelectricpower system.Calculationofthesymmetricalshort-circuitfaultcurrentis basedonsoftware simulationETAP 12.6. The conclusionisthatthe biggestfaultcurrent. The results
more » ... mmetricalthree-phasedisorders,thegreatestdisruptionoccursinLV MCCbus(400V) withinitialsymmetricalfaultcurrent(I "k) amountedto62.170kA,the maximum short circuit current (Ip)of 130.450 kA. Keywords: power systemanalysis, 3-phaseshortcircuit, ETAP.
doi:10.31000/jt.v5i1.338 fatcat:r5iibksxczekngvw56urtm554m