Penalty Model of Work Schedule Delay of Program under Contracted Environment Based on Sub-Network
2021
E3S Web of Conferences
Through the sub-network construction and the application of critical path method, this paper analyzes the impact of work schedule delay on the schedule of contracted project itself, the success or contracted projects, other follow-up contracted projects, and the program on the basis of double-code network and related lemmas. Based on this, a penalty model of work schedule delay is constructed and a case study is carried out. The research results show that the penalty model of work schedule
doi:10.1051/e3sconf/202125102026