Optimized Installation Flow – A Strategy for Substantial Cycle Time Reduction
2020
Proc. 28th Annual Conference of the International Group for Lean Construction (IGLC)
unpublished
Industrial system infrastructure installations, such as those in semiconductor fabrication plants, are complex, short-term and mission critical. They frequently encounter productivity, predictability and performance problems. We propose a strategic approach to manage such projects and substantially reduce their durations. The method, called Optimized Installation Flow (OIF), builds on lean and associated theories in the realm of production planning and control, synthesizing a method with seven
doi:10.24928/2020/0080