PRODUCTIVITY ANALYSIS OF INTERIOR WOODEN FRAME WORK IN ONE-UNIT-AT-A-TIME REFURBISHMENT OF APARTMENT HOUSE
集合住宅の戸別改修工事における木製内装下地工法の生産性分析

Yasuo OMI
2012 Journal of Architecture and Planning (Transactions of AIJ)  
In order to verify the effectiveness of new methods of work aiming at the productivity improvement in one-unit-at-a-time refurbishment of apartment house, I investigated and analyzed man-hour data of a new method of interior wooden frame work named "Gi system" in consideration of practice effect and comparative evaluation with the conventional method of work. At first, productivity of "Gi system" was inferior to the conventional method of work. But after practice effect, it decreased by 30%-50%
more » ... and surpassed that by 15%-50%. It means there is room for productivity improvement even in discontinuous and scattered interior refurbishment work by using suitable new method of work.
doi:10.3130/aija.77.2619 fatcat:ss4wgbix25a7jdmdfqu3o6w3na