EFFECT OF PIPE ROUTING ON TURBINE FLOW METER READINGS AND SUBSEQUENT DISCREPANCIES IN CONDENSATE LOADING AT BANGORA GAS FIELD
unpublished
In this Q1 of 2012 there are eighty one producing wells of natural gas in Bangladesh among which four belong to the Bangora Gas Field located at Muradnagar, Comilla. The production rate from this field rounds about 105 MMscfd of natural gas along with 330 bbl condensate per day. On an average five to six tankers are loaded everyday at Bangora Central Processing Facility for exporting the produced condensate. This loading purpose is served with two centrifugal pumps (P-640A and P-640B) which are