Repetitive construction processes scheduling using mixed-integer linear programming
2015
Budownictwo i Architektura
Many construction projects contain several identical or similar units, such as floors in multistory buildings, houses in housing developments, sections of pipelines or highways. Repetitive processes arise from the subdivision of a generalized construction process into specific activities associated with particular units. In many cases it is possible to perform individual processes (repeated in each units) in alternative ways (modes). Regardless of the construction project procurement system,