An efficacy of Zobe dam for hydroelectricity generation in Katsina State, Nigeria
2021
Nigerian Journal of Technology
The quest for other alternative and sustainable energy prompted the feasibility assessment of Zobe dam meant for irrigation to produce electricity; In this write-up the scheme is designed to operate with two turbines; turbine T1 to operate all year round to take account of the irrigation need downstream, The second turbine T2 will operate on a spill discharge, and to be available for four months with a generation capacity of 0.969 MW. T1 is expected to discharge 55,500,000m3 within six months
doi:10.4314/njt.v39i4.32