DEVELOPMENT OF LOW NOISE TRAVELING-WAVE TUBES (Phase 3: Environmentalization)
[report]
1962
unpublished
The preliminary designs for the improved M2108 and M2110 packages have been completed and the parts are being fabricated. The new designs provide for O-ring seals at all potential leakage points, and are of a more rugged mechanical design. The program is behind schedule due to a delay in the M2108 environmentalization. This delay is due, in part, to a delay in obtaining the M2108 humidity and salt spray data, and due to a redesign of the M2108 package that is more extensive than originally