Integrated evaluation of cost, schedule and emission performance on rock-filled concrete dam construction operation using discrete event simulation
2013
2013 Winter Simulations Conference (WSC)
Massive concrete dam projects will be conducted in the next ten years to respond to the increasing demand for clean energy and water resources in developing countries. With more attention paid to environmental issues, there is an increasing need to develop a methodology for reliably predicting the integrated performance of cost, schedule and emission factors in the planning stage. In this paper, we propose a methodology for using discrete event simulation (DES) for dam construction processes to