Schedule Delay Risk Analysis in Construction Projects with a Simulation-Based Expert System
2020
Buildings
In this paper, we present a simulation-based approach for effectively estimating delay risks in project schedules and predicting the possibilities of in-time project completion for various deadlines. The main contribution of this study is the development of a novel approach for duration risk quantification, which uses a newly introduced equation for total risk estimation regarding activities' durations, and quantifying the manager's experience as expressed through a questionnaire. In addition,